Department of Energy Analysis Says Coal Carbon Capture Project Would Emit More Greenhouse Gases Than It Stores

 

 

September 14, 2023 - An environmental assessment published by the Department of Energy found that Project Tundra, a major coal carbon capture project proposed in North Dakota, would emit more greenhouse gases than it stores.

The environmental assessment also “includes numerous egregious errors” and “does not even meet the basic standards” for a life cycle assessment, according to Dr. Emily Grubert, former deputy assistant secretary of carbon management at the Department of Energy.

As the Department of Energy considers funding the coal carbon capture project, documents show that cost estimates for Project Tundra have nearly doubled, engineering studies have taken three times as long as initially planned, and emissions reductions claims have been scaled back.

Environmental assessment concludes Project Tundra will emit more carbon than it stores

The Department of Energy (DOE) published an environmental assessment of Project Tundra in August, as part of its obligation under the National Environmental Policy Act to analyze the potential impacts of funding the carbon capture project. DOE is proposing to provide half of the estimated $77 million to construct injection wells designed to sequester carbon dioxide captured from the Milton R. Young power plant, a 50-year lignite coal plant near Center, North Dakota.

Minnkota Power, the generation and transmission association that operates the coal plant, said in June that it has also applied for a $350 million grant from the DOE Carbon Capture Demonstration Projects Program to help fund the construction of the carbon capture facility. Project Tundra is unlikely to be built without DOE funding; in a presentation last year to the National Association of Regulatory Utility Commissioners, Project Tundra consultant David Greeson said that “we’re really counting on a demonstration grant from the Department of Energy.” The DOE environmental assessment also found that Project Tundra likely “would not be constructed” without federal funding.

The environmental assessment includes a life cycle analysis that determined that “There is an expected 3.23 kg of CO2e emitted per kg of CO2 stored.”

 

In an op-ed published in UtilityDive, Dr. Grubert noted “the analysis suggests that the project would emit more than three tonnes of CO2 equivalent per tonne of CO2 stored, and still recommends moving forward — a deeply alarming sign for a project whose entire purpose is to reduce GHG emissions.”

DOE did not provide a response to a question from EPI: Why is DOE proposing to fund a carbon capture project that it expects will emit more greenhouse gases than it sequesters?

Dr. Grubert also submitted a comment to DOE detailing some of the errors in the environmental assessment, and pointed to some of the most egregious errors in her op-ed:

The errors in the draft EA’s life cycle analysis of GHGs are numerous and often structural, but for illustration, the analysis overestimates one value by a factor of 23,500 without so much as a comment that the value seems unusually high. It also claims that the capture unit would require about three times as much coal-fired power as the power plant is capable of producing, but that this would not lead to any additional GHG emissions. These are basic competency errors that suggest either total inattention to this crucial analysis, or a startling lack of capability.

A spokesperson for DOE did not provide EPI with an explanation for the errors in the environmental assessment, stating only: “The Draft Environmental Assessment (EA) for the proposed North Dakota CarbonSAFE: Project Tundra is available for public comment until September 19, 2023.”

The life cycle analysis of Project Tundra in DOE’s environmental assessment was completed by Burns & McDonnell, according to an appendix.

Project Tundra engineering study took three times longer than expected

The DOE environmental assessment for Project Tundra says that “If approved, construction is anticipated to begin in 2024 and to be complete by 2028.” If Project Tundra is built and completed by 2028, that would mean it took about 12 years in total, since it was proposed in 2016 by North Dakota’s Senators and coal industry lobbyists.

Project Tundra has suffered several delays and missed deadlines for completing engineering studies and beginning construction. In 2020 and 2021, the Project Tundra website claimed: “Project Tundra is in the advanced research and design phase. If the project moves ahead, construction will commence in 2022-2023.”

Engineering and design studies for Project Tundra have taken far longer than originally planned, and quarterly reports with updates about the studies show higher than expected costs, and the departure of a key contractor. Minnkota Power submitted the quarterly reports to DOE, which provided a $9.8 million grant for the engineering studies; EPI obtained the reports through FOIA requests.

The DOE-funded engineering study was originally expected to take 15 months, from October 1, 2019 until December 31, 2020. But DOE extended the deadline to complete the engineering study six times, resulting in a 45-month timeline ending in June 2023.

DOE initially extended the deadline to complete the engineering study by six months in December 2020; it then provided another six-month extension in June 2021, a third six-month extension in Fall 2021, a fourth six-month extension in February 2022, a fifth six-month extension in June 2022, and a sixth six-month extension in January 2023.

A Government Accountability Office report in 2021 documented problems with DOE’s carbon capture program, including that “DOE’s process for selecting coal projects and negotiating funding agreements increased the risks that DOE would fund projects unlikely to succeed.” The GAO report specifically noted: “According to DOE documentation and officials, senior leadership directed actions to support projects even though they were not meeting required key milestones.”

Project Tundra counts at least one key senior DOE leader as a proponent; before he took a job leading the DOE office focused on carbon capture projects in 2022, Brad Crabtree promoted Project Tundra as , including in 2017 letters urging Congress and President Trump to fund eight specific carbon capture projects. When President Biden nominated Crabtree, the executive director of North Dakota’s coal industry lobbying group congratulated Crabtree, saying: “We consider it a unique opportunity to have a native son of North Dakota to be selected for your position as assistant secretary for fossil energy and carbon management.”

The GAO report webpage shows that the recommendations made by GAO to DOE remain open, meaning that “actions to satisfy the intent of the recommendation have not been taken or are being planned.”

Cost estimates for Project Tundra have nearly doubled

Along with those delays, the cost estimates to build Project Tundra appear to have nearly doubled over the last two years, from “approximately $1 billion” at the beginning of 2022, to $1.45 billion according to reporting in March 2022, and more recently to $1.94 billion, according to a March 2023 presentation to DOE. 

The last slide of that presentation to DOE notes: “Capital cost – $1.94 billion,” and two other slides also describe the estimated cost: “Total Project CAPEX – $1,938MM”

In 2019, Minnkota Power estimated that Project Tundra would “cost approximately $1 billion,” and that figure was included on the Project Tundra website in a “Project Tundra By The Numbers” section throughout 20202021, and early 2022.