North Carolina Approves Duke Energy Plant to Extend Coal Use, Add Natural Gas

 

 

November 17, 2026 - North Carolina utility regulators on Monday approved a new long-term energy plan for Duke Energy that extends the life of some coal-fired power plants, calls for nearly 3,850 megawatts of new natural gas generation, and keeps the door open for new nuclear power plants.

The North Carolina Utilities Commission's Carbon Plan and Integrated Resource Plan outlines how Duke will meet growing electricity demand while balancing reliability, affordability, and energy security.

The decision comes as energy-intensive data centers, advanced manufacturing, and population growth are driving projections of increased electricity demand across the Carolinas.

Among the major provisions of the order:

  • Coal: Extend certain coal plant retirement dates beyond those approved in 2024.

  • Natural gas: Pursue approximately 3,841 megawatts of new generation between 2030 and 2033.

  • Solar: Procure up to 2,300 megawatts of new solar generation between 2032 and 2034.

  • Battery storage: Develop up to 2,700 megawatts of additional storage, bringing planned system capacity to as much as 5,400 megawatts by 2034.

  • Nuclear: Extend authorization for up to $440 million in advanced nuclear development costs through 2028, including preserving options for small modular reactors or a larger conventional reactor.

  • Hydropower: Authorize up to $55.6 million in near-term development costs for an expansion of pumped-storage hydropower.

The commission also authorized additional nuclear licensing work at the Shearon Harris site in Wake County and the W.S. Lee site in South Carolina. Regulators will convene a technical conference in 2027 to examine nuclear technology, costs, financing risks, and customer protections before deciding whether to move forward with construction.

The order is the first biennial Carbon Plan decision since North Carolina lawmakers eliminated the state's interim requirement to reduce power-sector carbon dioxide emissions by 70% by 2030 in 2025. The state retains its goal of carbon neutrality by 2050.

Coal and natural gas generation produce carbon dioxide emissions that contribute to climate change.

The commission's decision follows 12 days of expert witness hearings and five public hearings. More than 600 people submitted consumer statements.

Four commissioners unanimously approved the order. Commissioner Donald van der Vaart did not participate.

Duke Energy is expected to submit its next proposed Carbon Plan in fall 2027, when regulators will reassess electricity demand, technology costs, and resource availability.